Reconstruction of the ground surface on the Őrmező side of the Kelenföld terminal of metro line 4
muszaki_adatok_cim
Technical data
Building trades
utility design
electrical and mechanical design
telecommunication design
geotechnics
Principal
Mérték Építészeti Stúdió Kft.
Design value
18.00 millió Ft
Years of completion
2014 to 2015
Years of construction
2015
Design of external utility services for the bus terminal proposed at the Őrmező exit of the Kelenföld terminal of metro line 4 and a P+R multi-storey car park at the approval and detailed design level.